How we deliver an inspection project
Six stages from requirement to handover. Each one ends with a document you sign off before the next one starts.
Technical review: Frank GuoReviewed
An addaScan project runs in six stages: requirement definition, a sample test on your own parts, design and quotation, build with a factory acceptance test (FAT), installation with a site acceptance test (SAT), and training and handover. The acceptance criteria are agreed before the station is built, and each stage ends with a written record, so scope, cost and what counts as working are clear before the shutdown window.
What happens at each stage
Read across a row to see who does what, and what must be true before the project moves on.
-
Stage 01
Requirement definition
- You provide
- A description of the product and the defects, how they are found today, line speed, space available and what a missed defect costs.
- We do
- Clarifying questions, a first look at feasibility, and a site visit where needed.
- Document
- Written requirement: products, defects to catch, line conditions, constraints.
- Gate to next stage
- Requirement agreed, and samples available for testing.
-
Stage 02
Sample test
- You provide
- Good and defective samples that represent real production, including borderline cases.
- We do
- Image the samples under candidate cameras, lenses and lighting; record what is and is not visible.
- Document
- Feasibility conclusion with example images, limits and open risks.
- Gate to next stage
- The defects that matter are shown to be visible and repeatable.
-
Stage 03
Design & quotation
- You provide
- Access to PLC details, drawings or photos of the mounting position, and the shutdown windows.
- We do
- Station architecture, reject and PLC interface, mounting, licences, scope and exclusions.
- Document
- Proposal and quotation, including the acceptance criteria for FAT and SAT.
- Gate to next stage
- Proposal accepted and acceptance criteria signed off.
-
Stage 04
Build & FAT
- You provide
- The agreed FAT samples, and attendance at the FAT if you want to witness it.
- We do
- Build the station, develop the recipes, and test against the agreed samples before delivery.
- Document
- FAT record: tests, results and any open points.
- Gate to next stage
- FAT criteria met, or open points agreed in writing.
-
Stage 05
Installation & SAT
- You provide
- Access to the line, production time for testing, and your electrician or PLC programmer where changes are needed.
- We do
- Install, connect to the PLC and reject, tune on real production, test changeovers and fault handling.
- Document
- SAT report against the agreed criteria.
- Gate to next stage
- SAT criteria met on your line.
-
Stage 06
Training & handover
- You provide
- Operators and technicians available for training.
- We do
- Train operators and technicians; hand over recipes, backups and documentation.
- Document
- Signed handover, documentation set and support plan.
- Gate to next stage
- Station in production use, with support terms agreed.
FAT and SAT compared
Image processing that works on the bench does not prove the reject works on the line. That is why there are two tests.
| Factory acceptance test (FAT) | Site acceptance test (SAT) | |
|---|---|---|
| Where | Before delivery, on the built station | On your line, after installation |
| Products | The agreed FAT sample set | Real production, plus seeded defect samples |
| Tests | Detection of each defect, false rejects on good samples, recipe changeovers, outputs | The same at line speed, plus reject and confirmation, PLC signals, fault behaviour, operator workflow |
| Who attends | addaScan; you may witness | addaScan and your production, quality and maintenance team |
| Result | FAT record with any open points | SAT report; basis for handover |
Two numbers pull against each other
We define both, with the sample set and method, in the proposal.
False reject rate
The share of good products rejected. Measured on a known number of good products at production speed. Too high, and the station wastes product and loses operator trust.
Missed defect rate
The share of defective products that pass. Measured by feeding defective products at known positions. For critical faults the target is set with you; small runs cannot prove zero.
Reject confirmation
Evidence that each failed product actually left the line. Without it, a missed reject looks like a working station.
What you receive at handover
The station must stay useful after we leave. This is the handover set, confirmed in the proposal.
Documentation
Station description, wiring and I/O list, PLC interface description, and operating instructions.
Recipes and backups
Recipe files per product and a full backup of the station configuration.
Training
Operator training for daily use and technician training for cleaning, reference checks and new products.
Support plan
Who to call, what is covered, how remote help works, and the recommended spare parts list.
Delivery questions
How is an inspection project tested, commissioned and handed over?
What is tested during FAT and SAT?
How are false rejects and missed defects measured?
Can machine vision be retrofitted to an existing line?
What maintenance does a station need after handover?
What is included in a turnkey station?